We've decided to use CLT (cross-laminated timber) pannels in our project in order to make a fast and light modulated constructions. Our project is going to be based on modular construction, and some parts of the project are going to be risen so that the old parts of the cortijo don't have to be torn down.
The system we will use to make this construction can be found on www.healthwood100.es. It's a enterprise that provides CLT pannels with their own assemblying method and that are prefabricated in the industry.
Click here to see a video with images of the mounting of the pannels.
system it's possible to build a 250 m2 dwelling in 5 days. So taking into account this information we have estimated a total duration of 20 days (nearly 3 weeks) of construction until we finish the site works.
According to the website, using this
This is for example, a house built in 5 days using this system.
They follow 5 different steps to make the prudction of pannels accurate and fast:
-Manufacturing the pieces to measure.
-Placing the breathable sheet(stapled)
-Placing the timber-fibre made insulation sheet (16 cm)
-Putting SATE system: mortar layer, structural net, second mortar layer and the finish mortar.
-Placing the inner finishing: rastrel columns and placing the gypsum sheet(with installations inside.
Referring to the project, we have already finished with all the program distribution, as well as deciding all the elements and materials that are going to be used in the building. The result of this process is the following.